Excel WBS and Gantt Chart - XLGantt How to #6 – Managing Schedule Change

In Excel Gantt, you can use actual start and finish dates. So You can identify the schedule is delayed or ahead by entering the actual start and finish dates.

1. Schedule change management setting

Click the "Options" button on the ribbon menu > XLGantt tab to choose schedule option.

Schedule change management setting

 

If you choose "Managing Schedule Changes",  the following fields are displayed: Actual Start Date, Actual Finish Date, and Actual Total Work.

Schedule change management

 

2. How to enter the changed schedule

There are three ways to enter the changed schedule.

1) When the task is finished and you enter the actual start date and actual finish date.

  • If you enter the actual start date and the actual finish date directly, the %Work Complete is automatically entered as 100%.
  • If the planned schedule differs from the actual schedule, the background color of the date is displayed in yellow and the Gantt chart displays the actual schedule in blue lines.

XLGantt(Excel Gantt) – Managing Schedule Change

2) If a task is finished as planned

If a task is finished on the same schedule as the planned schedule, you can enter 100% of the %Work Complete only. If you do not enter the actual start date and actual finish date, they will be filled with the same date as the planned start date and finish date.

 

3) If a task is not finished yet

If a task is not finished, enter only the actual start date and the %Work complete. If you enter the actual finish date, the task is considered finished, so you only need to enter the actual start date.

 

[ XLGantt(Excel Gantt) How to ]

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top